Aquatica Environmental Consulting, LLC

425.802.8988

King County Critical Area Determinations (CAD)

 

The first step towards development of a property in King County that will require an on-site septic system is going through the County’s Critical Areas Designation (CAD) process.  Any wetland or stream near a proposed development activity must be flagged on-site and a report submitted to the County.  This is the work that Aquatica Environmental Consulting performs. 

 

How far away do you need to stay to avoid having to have the wetland delineated?  It is variable and is currently determined on a case-by-case basis.  The precise distance depends on the buffer width and the proximity of the development.  Depending on the location of the wetland and future development, the wetland may need to be surveyed by a licensed land surveyor. Aquatica does not provide this service.

 

Following receipt of Aquatica’s report, the County will visit the site and verify the delineation and wetland/stream classification.  The County then writes a CAD letter, summarizing critical area restrictions.  This process may take 6-8 weeks following submittal of the completed CAD application. How long it takes depends on the County’s work load.  After you receive the CAD letter from the County, you then can apply for an on-site septic permit from the health department.  Approval from the health department may take 3 months or more.  A building permit usually can not be applied for until after the septic permit has been applied for at the health department.

 

Mitigation

The County only allows the disturbance of wetlands, streams, or their buffers when it can not be reasonably avoided.  One common impact that occurs and is allowed is when it is necessary to cross a wetland, stream or buffer to access a property.  Another common situation is buffer averaging.  This occurs when it is necessary to reduce the buffer in one area, and there is room to replace it elsewhere.  This can allow for a smaller buffer width in one area to allow development, while increasing the width elsewhere.  Whenever there are wetland, stream, or buffer impacts, it is necessary to “mitigate” the impacts.  This requires the preparation of a report and plan that describe exactly where the impact is, how much area is involved, and what is proposed to off-set the environmental impacts of the project.  The mitigation required typically involves removing invasive vegetation and installing native trees and shrubs. 

 

With the large buffer widths on streams and wetlands, there are now many properties that are almost entirely constrained by wetland/stream and buffer.  In those situations, modest development on the property is usually allowed, although it is necessary to get what is called a critical areas alteration exception or reasonable use exception.  In this instance, it is necessary to go through the SEPA process (see below), so this process takes more time than a typical project where such challenges do not occur.  There are also associated County fees that may be close to $10,000.  Properties that have to go through this process also require mitigation, which adds additional costs.  Additionally, the County limits the amount of area that can be disturbed, which may limit the size (foot print) of the house, type of septic system and limit the property owner to a small area of lawn/ornamental landscaping.  Aquatica can assist clients by preparing mitigation plans and assisting with the alteration/reasonable use processes. 

 

Construction Review

Following the approval of a mitigation plan, the project can be implemented.  Plan implementation is required before the County will give final approval on a completed construction project, such as prior to allowing a building to be occupied.  Aquatica can assist Clients by recommending landscape maintenance contractors to implement the plan.  It is also recommended that a biologist from Aquatica inspect the plants and their planting locations prior to installation. 

 

There are several benefits to having Aquatica review the project prior to installation.  Occasionally site conditions change and it is necessary to modify the plant species or their locations to ensure that the plants will thrive once installed.  Sometimes landscape contractors inadvertently obtain an ornamental species rather than native species, which then must be replaced.  Occasionally a nursery or contractor will try to install “cheap” plants that are not of the required size or of poor health.  Sometimes nurseries sell small plants in large pots that have not yet grown roots to fill the pot.  In this situation you are buying soil when you want to buy plant roots!  With a minimal amount of time, Aquatica can help Clients ensure that mitigation plantings get off to the best start possible and that the Client is getting what they are paying for.  This is important due to the amount of money that has likely been invested in the project so far, and because there is a monitoring period (see below) in which the success of the plantings are monitored.  The applicant is required to ensure that the majority of the plants not only survive, but thrive for a period of time. 

 

Monitoring

After a mitigation plan is implemented (weeds removed, plants installed, etc.), the County requires that the area be monitored for three to five years, depending on project complexity.  This requires two site visits per year and annual reports that summarize the condition of the site.  Monitoring typically includes identifying plants by species, counting them to determine if sufficient plants have survived, measuring their growth and providing maintenance recommendations to ensure project success.  Aquatica can assist with monitoring and submission of reports to the County. 

 

Additional Government Regulations

The State/County recently have required that any project that disturbs more than 1-acre (through clearing or grading) or requires a hydraulic permit application for in-stream work (HPA) must go through the State Environmental Policy Act (SEPA).  SEPA is also required for larger development projects and alteration/reasonable use exceptions.  This process can take a few months and requires a public notice period, during which the public can comment on the project.  SEPA can be done concurrently with the building permit.  Clearing of property involving tree removal requires a forest practices application (FPA) to obtain a permit from the Department of Natural Resources.  The FPA can not be applied for until after a SEPA decision has been made.  Aquatica can assist with both SEPA and FPA permitting. 

 

Recommendations

If you need a septic designer, surveyor, house designer, well installer, geotechnical consultant or general contractor for home building, Teresa, our wetland specialist, can make a recommendation.  She and her husband have built a home in unincorporated King County and have personal experience with the “process”.  And yes, it is a process!

Aquatica Environmental Consulting, LLC 425.802.8988

Copyright 2007-2010 Aquatica Environmental Consulting, LLC. All rights reserved.